Blower Unit: Installation
- INSTALL BLOWER ASSEMBLY
- Install the blower assembly with the claw in the order shown in the illustration.
- Install the blower assembly with the bolt and 3 screws.
Torque: 9.8 N*m (100 kgf*cm, 7 ft.*lbf) for bolt
- Connect the 3 connectors.
- INSTALL AIR DUCT (See INSTALLATION )
- INSTALL ECM (See INSTALLATION )
- INSTALL INSTRUMENT PANEL SUB-ASSEMBLY LOWER
- Install the instrument panel sub-assembly lower (see INSTALLATION ).
- INSTALL INSTRUMENT PANEL SUB-ASSEMBLY UPPER
- Install the instrument panel sub-assembly upper (see INSTALLATION ).
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
- PERFORM INITIALIZATION
- Perform initialization (see INITIALIZATION ).
- INSPECT SRS WARNING LIGHT
- Check the SRS warning light (see DIAGNOSIS SYSTEM ).