Removal and Installation: Installation
WARNING: This page is about a different car, the 2005 Nissan Titan. However, it is still accessible from the selected car via links, so may be relevant.
- Apply liquid gasket to joint part of cylinder head and camshaft bracket following the steps below.NOTE: Illustration shows an example of left bank side (zoomed in shows No.1 camshaft bracket).
- Refer to illustration "a" to apply liquid gasket to joint part of No.1 camshaft bracket and cylinder head.
- Refer to illustration "b" to apply liquid gasket 90° to illustration "a".
Use Genuine RTV Silicone Sealant or equivalent. Refer to " RECOMMENDED CHEMICAL PRODUCTS AND SEALANTS " .
- Install the rocker cover.
- Make sure the new rocker cover gasket is installed in the groove of the rocker cover.
- Tighten the bolts in two steps in the numerical order shown.
1st step: 2.0 N.m (0.2 kg-m, 18 in-lb)
2nd step: 8.3 N.m (0.85 kg-m, 73 in-lb)
CAUTION: Do not hold the rocker cover by the oil filler neck (right bank).
- Install the PCV hose.NOTE:
- Remove foreign materials from inside the hose using compressed air.
- The inserted length is within 25 - 30 mm (0.98 - 1.18 in) [Target: 25 mm (0.98 in)].
- Installation of the remaining components is in the reverse order of removal.