Injector Nozzle Fuel Lines: Installation
- To install, reverse removal procedure. Clean intake manifold and cylinder head gasket mating surfaces. Install intake manifold on cylinder head, with new gasket, making sure inlet port is installed in turbocharger crossover pipe.
- Tighten intake manifold bolts to 14-17 ft. lbs. (20-24 N.m) and tighten crossover pipe boot clamp. Connect turbocharger boost pressure indicator switch connector.
- Install diagnostic plug bracket and tighten bolts to 14-17 ft. lbs. (20-24 N.m). Connect battery ground cable. Start engine and check for intake leaks.